>Home >Building

Building

There are two important building projects that the church board has voted to recommend to the church members for review and vote. Our intent is to reach more members by providing this information electronically instead of having an in-person church business meeting. 

How to vote:

  1. Please review the two proposals below.
  2. Respond to the text you received with two separate responses, either YES or NO. Here is an example: 
  • Roof: YES or NO
  • Gym floor: YES or NO

 

School roof

Motion summary: After reviewing several bids, the church board recommends the bid from American Roofing, Inc to replace the school roof. 

Cost: $74,500

Scope includes installation of a new, white, solar ready GAF Everguard 60mil TPO
thermoplastic roofing system on the existing 4750 sq. ft school roof. The installed system will carry an extended 31 year warranty. Review the complete bid for additional details.

 

Gym floor

Motion summary: After reviewing several bids, the church board recommends the bid from First Choice Concrete Surfaces to redo the 2536 sq. ft. gym floor.

Cost: $24,288

The following process will be followed:

Step 1: Grind and patch floor

Step 2: Install moisture vapor barrier

Step 3: Apply heavy duty epoxy at 10mm

Step 4: Apply heavy duty epoxy at 10mm again

Step 5: Sand and paint basketball and volleyball lines

Step 6: Apply HW urethane nonslip

Limited warranty included.